Martin Way AC Water Main

We installed an 8″ AC main replacement along a commercial corridor for The City of Olympia. ┬áThis project included boring 3200 feet of Certainteed pipe, 6 hydrants and 8 services. ┬áThis project also required night-time cut over from existing.

Certainteed Certa-Lok C900RJ Installation Video of Wiseman Utilities Crew at work. Best Installation crew I’ve seen in Washington State! 3200′ 8″ C900RJ Certa-Lok was ordered on Thursday, Shipped on Friday from Kansas and Delivered on Tuesday for Wednesday install. Pipe was ordered due to two failed pull-backs of Diamond-Lock material… ultimately rejected on site, pulled out and chainsawed up. Certainteed saves the day again! For Washington, Oregon, Idaho and Alaska… contact Antec Corporation – North Bend WA for more information on Certa-Lok”